Quantitative Effects of Construction Changes on Labor Productivity¶
Thomas, & Napolitan. (1995). Quantitative Effects of Construction Changes on Labor Productivity.
Cited by¶
1 citation across 1 artifact.
Each citation links to the sentence it supports in the citing article.
Domain-specific¶
- Requirements Churn
- Work already installed is demolished and redone; trades stand idle waiting for a stable drawing set, generating documented standby and acceleration costs; and the mismatch surfaces as disputed change-order claims and schedule overruns
This sourceA quantitative study finding an average 30% loss of labour efficiency when construction changes are performed, with disruptions during change work.
Supported in partVerified against the publisher's abstract
“the average effect of all changes was a 30% loss of efficiency”
- Work already installed is demolished and redone; trades stand idle waiting for a stable drawing set, generating documented standby and acceleration costs; and the mismatch surfaces as disputed change-order claims and schedule overruns
Verification¶
Does it exist? Not checked yet. This work's DOI is recorded above but has not been resolved against an external catalogue, so nothing here confirms the work exists.
Does it back the claim? Read against the text for 1 of 1 citation: 1 supported in part. Each verdict is shown under its citation below, with what in the work backs the sentence.
Support is checked per citation rather than per work — the same source can be cited soundly in one article and wrongly in another. Per-citation recording began recently, so a citation with no recorded check is a gap in the record rather than evidence it went unchecked.
See how references were verified.
Registry ID ref:da6b1ac9ec40 · see in the full table